Project title: Wood pellet manufacturing plant
Investor: RST Pellet d.o.o.
Location: Delnice, Croatia
Construction completion: 2019
Project description
Reasons for investing:
- Production of high quality pellets due to market demand 75 000 tons of annual input of biomass as raw material are planned and a production of up to 40 000 tons of finished product-pellet per year. The pellet producing plant and biomass boiler use forest biomass as raw material.
75 000 tons of biomass per year (with 35% moisture) need to be ensured. About 55 000 tons are used for the production of 40 000 tons of pellets, while the rest is used for boiler needs.
Enerkon participated in the project through following activities:
- Main design
- Detailed design
- Supervision of Mechanical works