Project name: Hazardous waste thermal treatment plant
Investor: ZGOS, City of Zagreb
Location: Zagreb, Croatia
Construction completion: 1997
Project description
Reasons for investing:
- Jakuševac landfill rehabilitation
- Disposal of hazardous waste from various manufacturers
- Environmental protection
Technical characteristics of the plant:
- Disposal capacity of 1250 kg/h of solid, liquid and sludge waste
- Primary chamber designed as a rotary kiln
Enerkon participated in the project through following activities:
- Participating in the Environmental Impact Assessment
- Preliminary Design and obtaining a Location Permit
- Main Design and obtaining a Building Permit
- Detailed design and Supervision of Mechanical works over the construction
- Commissioning and obtaining the Use Permit